Business & Economics
Meta Breaks Ground on 1-GW Alberta AI Data Centre, Locks In Private Gas & Power Deals
On 9 July 2026 Meta formally committed CAD 13 billion (≈US$9.2 billion) to build a 1-gigawatt artificial-intelligence data-centre campus in Sturgeon County, Alberta—its first in Canada—and simultaneously secured its own 932 MW gas plant and a separate 250 MW decade-long supply contract to power it.
Focusing Facts
- Project will employ ~3,000 workers during construction and create 300 permanent jobs, according to the Alberta government release of 9 July 2026.
- Meta is fully funding the CA$4.6 billion Greenlight Electricity Centre (970 MW natural-gas) and a 250 MW+10-year energy supply agreement with Capital Power, scheduled to start delivering in H2 2028.
- Alberta expects to collect about CAD 250 million a year in royalties, taxes and fees once the facility is operational.
See how 3 sources reported this story.
- ✓ Full multi-perspective analysis on every story
- ✓ Primary source links for every claim
- ✓ Daily email briefing — no algorithm
Perspectives in this article
- Pro-business outlets
- Environment-minded general news outlets
- Investor-focused financial commentary