Meta Breaks Ground on 1-GW Alberta AI Data Centre, Locks In Private Gas & Power Deals

On 9 July 2026 Meta formally committed CAD 13 billion (≈US$9.2 billion) to build a 1-gigawatt artificial-intelligence data-centre campus in Sturgeon County, Alberta—its first in Canada—and simultaneously secured its own 932 MW gas plant and a separate 250 MW decade-long supply contract to power it.

By Underlines Team

Focusing Facts

  1. Project will employ ~3,000 workers during construction and create 300 permanent jobs, according to the Alberta government release of 9 July 2026.
  2. Meta is fully funding the CA$4.6 billion Greenlight Electricity Centre (970 MW natural-gas) and a 250 MW+10-year energy supply agreement with Capital Power, scheduled to start delivering in H2 2028.
  3. Alberta expects to collect about CAD 250 million a year in royalties, taxes and fees once the facility is operational.

See how 3 sources reported this story.

Where they agree. Where they disagree. What they left out.

  • ✓ Full multi-perspective analysis on every story
  • ✓ Primary source links for every claim
  • ✓ Daily email briefing — no algorithm

Perspectives in this article

  • Pro-business outlets
  • Environment-minded general news outlets
  • Investor-focused financial commentary
Share

Related Stories